The newly renovated lower-level restrooms are now open and ready for use! The first-floor restroom renovations are now in progress.
Upgraded facilities now feature:
✅ New partitions – Enhancing privacy and providing a fresh, modern look.
✅ Fresh paint – Brightening the space with a clean and updated design.
✅ Upgraded lighting – Energy-efficient fixtures for better visibility and sustainability.
✅ Improved accessibility – Enhanced ADA-compliant features for ease of use.
✅ Sustainability upgrades – Water-efficient fixtures to reduce environmental impact.
We appreciate your patience during this renovation. Below is the planned schedule for upcoming restroom renovations:
🛠 Renovation Timeline:
🔹 1st Floor – Started the week of March 31 | Completion the week of May 5
🔹 2nd Floor – Starts the week of May 12 | Completion the week of June 16
🔹 3rd Floor – Starts the week of June 23 | Completion the week of July 28
🔹 4th Floor – Starts the week of August 4 | Completion the week of September 8
🔹 5th Floor – Starts the week of September 15 | Completion the week of October 20
If you have questions, contact us at hshsl@umaryland.edu or 410-706-7995.